By Forrest Crellin PARIS (Reuters) -Europe's leading data centre hubs face a major shift as developers will go wherever connection times are shortest, unless there is more proactive electricity grid

Europe's Data Centre Landscape May Shift Due to Poor Grid Planning

By Forrest Crellin

PARIS (Reuters) -Europe's leading data centre hubs face a major shift as developers will go wherever connection times are shortest, unless there is more proactive electricity grid planning, a report on Thursday by energy think-tank Ember showed.

Data centre buildout has exploded in recent years as tech companies race to put together the strongest offering of competitive artificial intelligence (AI) models, which rely on a new generation of power-hungry data centres.

This could lead to a geographical shift in investment in Europe as developers look for new places with easier power access and shorter lead times, the report said.

By 2035, half of Europe's data centre capacity could be located outside the current main hubs Frankfurt, London, Amsterdam, Paris and Dublin, the report said.

This could leech billions of euros in investments from the congested countries, as data centres in Germany contributed 10.4 billion euros ($12 billion) in GDP in 2024 which should more than double by 2029, and it could slow job growth, it said.

Only France, is expected to maintain continued data centre investment as the grid remains relatively unconstrained, the report said.

Connecting a new data centre to the grid in legacy hubs can take an average of 7–10 years, with some projects facing delays of up to 13 years, the report said.

However, wait times in newer markets are much shorter, with Italy taking just three years, it said.

"Grids are ultimately deciding where investments go ... they are now effectively a tool to attract investment," said Elisabeth Cremona, Senior Energy Analyst at Ember.

"In Europe's push for competitiveness and economic growth, it now needs to be taking into account grids and driving investment to that infrastructure if it wants to see other projects materialise," she said.

She added that this is not unique to data centres but covers all industry, as any kind of industry that is either new or looking to electrify is going to go through the same process.

In Sweden, Norway and Denmark, data centre electricity demand is expected to triple already by 2030. In Austria, Greece, Finland, Hungary, Italy, Portugal and Slovakia data centre consumption is projected to increase by three to five times by 2035 compared to 2024.

($1 = 0.8692 euros)

(Reporting by Forrest Crellin; editing by David Evans)

Key Takeaways

  • Poor grid planning could shift Europe's data centre locations.
  • Developers seek shorter connection times for new data centres.
  • Half of Europe's data centres may move from current hubs by 2035.
  • France expected to maintain data centre investment due to grid capacity.
  • Electricity demand for data centres to triple in Nordic countries by 2030.

Frequently Asked Questions

What could happen to Europe's data centre capacity by 2035?
By 2035, half of Europe's data centre capacity could be located outside the current main hubs such as Frankfurt, London, Amsterdam, Paris, and Dublin.
Which country is expected to continue data centre investment?
Only France is expected to maintain continued data centre investment as its electricity grid remains relatively unconstrained.
How long does it typically take to connect a new data centre in legacy hubs?
Connecting a new data centre to the grid in legacy hubs can take an average of 7–10 years, with some projects facing delays of up to 13 years.
What is the expected electricity demand for data centres in Scandinavia?
In Sweden, Norway, and Denmark, data centre electricity demand is expected to triple by 2030.
What is the impact of grid planning on investment in data centres?
Grids are ultimately deciding where investments go, and proactive planning is necessary to attract investment to infrastructure for competitiveness and economic growth.